The Residential South End
The Merced Avenue South End project was completed in December 2024, enhancing connectivity and safety for people walking and biking in the area. The improvements support active transportation and better access to nearby communities.
Project Benefits:
This project is part of broader efforts to create safer, more sustainable streets in the San Gabriel Valley. Stay tuned for updates on future improvements!
Project Construction Timeline: Phase I - South
Start of Construction Notices Distributed: December 2023
Project Benefits:
- Safer crossings and improved pedestrian access
- Enhanced bike infrastructure for better connectivity
- Increased mobility options for residents and visitors
- Support for sustainable and active transportation
- Improved access to local businesses and community spaces
This project is part of broader efforts to create safer, more sustainable streets in the San Gabriel Valley. Stay tuned for updates on future improvements!
Project Construction Timeline: Phase I - South
Start of Construction Notices Distributed: December 2023
- Community Engagement & Stewardship: February 2024 – June 2025
- Construction: January 2024 – December 2024
- Grand Opening Celebration: Early 2025
- Post Construction Water Quality Monitoring: January 2025 – December 2027
- Westside Improvements: January 2024 – June 2024
- Eastside Improvements: June 2024 – November 2024
- Street Repaving and Striping: October 2024 – December 2024